A rigid insertion method would have needed extra access pits at each bend. Instead, the liner was made to match the surveyed alignment, with built-in bend sections.
Wet-out and pull-in had to fit inside the resin's working time. Once the liner was in position, a bladder was inflated under control to press it against the host pipe through the straights and every bend, and the liner was then cured in place.
The main was renewed structurally along its existing route, with no additional openings.

Figures are taken from the project records. Client and site names are withheld.