We recently completed the rehabilitation of seawater cooling lines at an industrial site in Singapore. The pipes are DN1500 and DN1800, and the work was done in two phases, on day and night shifts.
Each line was flushed, jetted and inspected by CCTV before lining. A glide foil went in first. The Axion UV-cured GRP liner was then strapped, lifted by crane and pulled in from the access pit. Packers and end caps were fitted, the liner was inflated against the host pipe, and a UV light train was run through it to cure it.
After cooling, the liner ends were cut and sealed, and any finishing patches were made inside the pipe. A post-lining CCTV survey was carried out on every section before handover.


Figures are taken from the project records. Client and site names are withheld.