Years of corrosion had left the plant's pipework heavily encrusted. The pipes ran in short sections of 5 to 12 m, between existing equipment, with confined-space access and a fixed shutdown window.
We surveyed each section with a robotic crawler, cut the scale back with a chain cutter and finished with high-pressure jetting. Overlapping liner sections were then pulled in place, so the lining runs continuously from one section to the next.
Post-lining CCTV showed smooth transitions at every overlap, and pressure testing confirmed the lining was watertight. The lined pipes were back in service within 24 hours of lining, and the plant kept running throughout.


Figures are taken from the project records. Client and site names are withheld.