Personnel, vehicles and equipment all needed security clearance before they could enter the site. With a school next door, work areas and activity times were planned to keep pupils and staff well clear.
The main was heavily encrusted, so cleaning had to be thorough and fast. Liner and resin were airfreighted to meet the programme, and wet-out, pull-in, curing, end sealing and inspection were run back to back by our own team.
The main was renewed within the two-week window, with very little excavation on the estate.

Figures are taken from the project records. Client and site names are withheld.