Overview
A glass-fibre liner pre-impregnated with light-reactive resin is pulled into the host pipe and inflated. A UV light train then travels through it at a controlled speed, curing the liner precisely.
Curing typically takes hours rather than days, and every installation has an instrumented cure log. That makes UV lining the preferred method for busy roads and sensitive catchments.
We install the Axion UV liner system, which also suits large-diameter sewers and drinking-water mains.

How it works
- 01
Prepare
Pipe cleaned and inspected, lateral positions recorded.
- 02
Pull in
Factory-impregnated liner pulled in and inflated.
- 03
Cure
UV light train run at a logged speed and intensity.
- 04
Verify
Ends finished, laterals reopened and CCTV recorded.
Applications
- Sewers under live traffic
- Short possession windows
- Large-diameter sewers and drains
- Projects needing full cure traceability