Overview
A winding machine in the manhole spirals an interlocking PVC strip into the host pipe, forming a new pipe as it goes. The sewer can stay live throughout, so bypass pumping is often not needed.
Cementitious grout fills the space between the old pipe and the new lining, providing structural support and load transfer.
We deploy spiral-wound lining for pipes up to 3 metres in diameter. Where the project needs it, a CIPP liner can be installed inside the wound pipe for a smooth, sealed bore.
How it works
- 01
Set up
Winding machine installed in the access chamber.
- 02
Wind
Profile strip wound into the pipe under flow.
- 03
Grout
Annulus filled with cementitious grout.
- 04
Finish
Connections reinstated and CCTV recorded.
Applications
- Large trunk sewers
- Pipes that cannot be isolated
- Culverts and box sections
- Long drives between access points