800 m of live water main inspected in two days, with no shutdown

A tethered probe travelled with the flow, sending back live CCTV and leak data.

Cable drum and control unit set up at the access point.
Cable drum and control unit set up at the access point.
Pipe
DN700 to DN1200
Length
About 800 m
Method
In-line inspection, live main
Duration
Two days

Large water mains in the city centre cannot simply be switched off for a survey. These ones also had several offtakes, bends and a butterfly valve.

The probe went in through an air valve and travelled with the water flow, tethered to a cable. Operators watched live footage and data while keeping the cable release in step with the probe's movement.

The survey found possible leaks and air pockets and recorded the internal condition of the main, which gave the asset owner what it needed to plan targeted maintenance. Water supply was not interrupted.

Preparing the probe before launch.
Preparing the probe before launch.
Launch tube fitted to the air valve.
Launch tube fitted to the air valve.

Figures are taken from the project records. Client and site names are withheld.

Contact

Tell us about your pipeline.

Share the location, pipe size and material, length and the problem you are seeing. We will reply with next steps.

Coimbatore office
12B, Door No. 1996/7A, MR Garden
Narayana Avenue, Krishna Colony
Coimbatore, Tamil Nadu 641015, India

Your enquiry is sent directly to our office. We will reply by email.