A baseline survey of a large water main, while it stayed in service

130 m surveyed upstream from an air valve to a DN1800 butterfly valve.

Internal condition recorded during the survey.
Internal condition recorded during the survey.
Pipe
DN700 to DN1800
Length
About 130 m
Method
In-line CCTV and sonar
Supply
Maintained

The owner wanted a clear record of the main before planned works, so that any later inspection would have a baseline to compare against.

We deployed through the air-valve access once the clear opening was confirmed, and surveyed upstream along the agreed route. Every significant observation was logged against its distance along the main.

The footage showed possible leak points and trapped air, as well as the condition of the pipe wall, all without interrupting supply.

Deployment at the access chamber, with live monitoring on site.
Deployment at the access chamber, with live monitoring on site.

Figures are taken from the project records. Client and site names are withheld.

Contact

Tell us about your pipeline.

Share the location, pipe size and material, length and the problem you are seeing. We will reply with next steps.

Coimbatore office
12B, Door No. 1996/7A, MR Garden
Narayana Avenue, Krishna Colony
Coimbatore, Tamil Nadu 641015, India

Your enquiry is sent directly to our office. We will reply by email.